SMP-ECOLOGY GRANT DELIVERABLES
SMP-UpdatedBanner  

The documents and links below are the tasks performed and deliverables required by the Benton County-Washington State Department of Ecology Grant Agreement No.G1200022, for the Benton County Shoreline Master Program Update.  The links to the documents are shown by month in descending order.


Progress Report #11 - July 8, 2014
Benton County's Ecology Grant
Progress Report #11

Progress Report #10 - June 26, 2014

Benton County's Ecology Grant Progress Report #10

Deliverables:
Benton County's SMP Submittal Checklist - 6/26/14
Benton County's locally approved Final SMP Submittal to Ecology - 6/26/14

Tasks 5.1-5.7



Progress Report #9- April 18, 2014
Benton County's
Ecology Grant Progress Report #9

Deliverables:
Benton County's
Shoreline Restoration Plan - 4/20/2014
Proposed
Environment Designation - 4/20/2014
Benton County
Cumulative Impacts Analysis - 4/20/2014
No Net Loss Report
- 4/20/2014
Benton County's
SMP Submittal Checklist - 4/20/2014



Progress Report #8- January 16, 2014

Benton County's Ecology Grant Progress Report #8

Deliverables:

-Benton County's SMP Submittal Checklist 11/22/2013

-Final Restoration Plan 6/28/2013


November 2013
Benton County
DRAFT Cumulative Impacts Analysis 11/13/13

October 2013

-Draft Shoreline Public Access Plan 10/11/2013



Progress Report #7- October 21, 2013

Benton County's Ecology Grant Progress Report #7


Deliverables:

-Benton County's SMP Submittal Checklist 10/21/13

-DRAFT SMP Review Document 10/21/2013

-Exhibit Task A

-Exhibit Task C


August 2013


Deliverables:

-Benton County Full Visioning Survey Results 5/1/2013

-SMP Update Open House Notes 5/2/2013

-Benton County Visioning Survey Handouts 4/11/2013


July 2013


Progress Report #6- July 2nd, 2013

Benton County's Ecology Grant Progress Report #6 PDF Document


Deliverables:

-Final Analysis Report 4/17/2013

-SMP Submittal Checklist 6/28/2013

-Final Restoration Plan 6/28/2013



April 2013


Progress Report #5- April 20, 2013

Benton County's Ecology Grant Progress Report #5 PDF Document


Deliverables:

- Final Analysis Report 4/17/2013


Progress Report Documentation:

- Task C Implement Public Participation Plan- January Regional Public Forums

- Phase 2 Task 2.3 Final Analysis Report (linked above)

- Phase 2 Task 2.3 Complete Inventory Map Folio-Low Resolution 4/18/2013 PDF

- Phase 3 Task 3.1 Visioning Process- Community Questionnaire

- Phase 3 Task 3.2 Preliminary Goals and Policies

- Phase 3 Task 3.3 Draft Environmental Designations

- Phase 4 Task 4.1 Draft Restoration Plan




November 2012


Draft Analysis Report:

Preliminary Analysis Report:


*Shoreline Inventory Map Folio:

June 2012
  • Shoreline Master Program Update-Public Participation Plan
  • Shoreline Minimum Jurisdiction Maps (File size is too large for this webpage, please contact the Planning Department for original mapping) Low Resolution PDF maps of the Minimum Shoreline Jurisdiction may be accessed here.

February 2012

 


Page Updated -6/30/2014


       
       
       

       